WORK PROGRESS REPORT FOR PROPOSED ‘JUMEIRA HEIGHTS’ RESIDENTIAL DEVELOPMENT ON LR NO 209/99/25 PARKLANDS NAIROBI AS AT 06.08.2018
The project is on track as per works schedule. Currently the reinforced concrete structure is at level 9 of 18 (basement 01, 02, ground floor and first floor parkings plus residential units level 01 - 05). Level 10 slab and columns are ongoing, at an advanced stage. Walling has been completed on levels 01 -05 of residential units. Plaster to walls and soffits of ceilings have been completed up to level 03 of residential units. Electrical conduits and plumbing pipes are completed up to level 03 of residential units as well.